Time report for estimated time possible?

  • 3
  • 24

Hi list,

is it possible to create a time report for estimated time of issues in a project even if there is no worked time on the issues.
I would like to have a summary of the time that is estimated to be spent on the issues.

Thanks in advance.

Regards,
Tilman
Answered by andrey tigay
 
Hello Tilman,

Correct Time report requires logged work items in Spent time.
In your case it's possible to auto-log '0m' in Spent time via the workflow so that each time issue is created, Spent time is set to 0m.
Another way is just to set Spent time to 0m with the batch command - select all issues from target project on Issue list and start typing 'work 0m' -> Apply.

Thank you.
Hello Tilman,

Correct Time report requires logged work items in Spent time.
In your case it's possible to auto-log '0m' in Spent time via the workflow so that each time issue is created, Spent time is set to 0m.
Another way is just to set Spent time to 0m with the batch command - select all issues from target project on Issue list and start typing 'work 0m' -> Apply.

Thank you.
Regards,

Andrey Tigay
YouTrack engineer

Hello Andrey,

thank you very much. That works like a charm.

Regards,
Tilman

Tilman,

You are welcome!
Regards,

Andrey Tigay
YouTrack engineer